China Sourcing Timeline: From Idea to Delivery

TL;DR: First order from China typically takes 3–6 months end-to-end (2–4 weeks supplier search, 2–4 weeks sampling, 3–6 weeks production, 2–6 weeks shipping). Reorders are faster: 4–8 weeks. Custom OEM products take longer due to tooling and prototyping.

Complete Timeline Breakdown

StageDurationNotes
1. Research & Planning1–2 weeksProduct specs, HS codes, budget calculation
2. Supplier Search2–4 weeksSend RFQs, compare quotes, shortlist suppliers
3. Sampling2–6 weeks1–3 rounds of samples (2 weeks each)
4. Contract & Payment1–2 weeksFinalize terms, sign contract, pay deposit
5. Production3–6 weeksDepends on quantity, complexity, and factory capacity
6. QC Inspection2–5 daysPre-shipment inspection at factory
7. Sea Freight3–6 weeksPort to port + customs clearance
7b. Air Freight (alt)5–10 days3–5x more expensive than sea freight

Timeline by Product Type

Product TypeFirst OrderReorder
Off-the-shelf (logo only)6–10 weeks4–6 weeks
Modified existing product8–14 weeks4–8 weeks
Custom OEM (existing tooling)10–16 weeks6–10 weeks
Custom OEM (new tooling)16–24 weeks6–10 weeks

How to Speed Things Up

Chinese New Year Impact

Chinese New Year (CNY) is the single biggest disruption to China sourcing timelines. Factories close for 2–4 weeks, and it takes another 2–3 weeks for full production capacity to resume as workers return from their hometowns. Plan to place orders at least 6–8 weeks before CNY, or accept that orders placed in December–January will be delayed by 4–6 weeks.